Tasks & Hierarchy ​

Each task in the tasks array maps to one row. Row order follows array order.

Required fields ​

FieldTypeDescription
idstringUnique identifier
namestringDisplay name
startDate | stringStart date/time
endDate | stringEnd date/time

Optional fields ​

FieldTypeDefaultDescription
progressnumber0Completion 0–100
parentIdstring—Parent task id (16px indent per level)
collapsedboolean—Hide descendants when true
type'task' | 'milestone' | 'group''task'Row kind
showSummaryBarbooleantrueGroup summary bar on timeline
readOnlyboolean—Disable drag, resize, progress edits
dependenciesstring[] | GanttDependency[]—Predecessor ids
baseline{ start, end, color? }—Original plan overlay
colorstring—Bar fill color
sticky'top' | 'bottom'—Pin row while scrolling

Group rows ​

Set type: 'group' on parent rows for hierarchy and optional summary timeline bars.

showSummaryBarTimeline behavior
true (default)Summary bar with rolled-up dates/progress; child bars when expanded
falseNo bar on group row; children render their own bars

Parent rows with children show a ▸/▾ collapse button. Click toggles task.collapsed and updates via onTasksChange.

tsx
const tasks = [
  { id: 'phase', name: 'Phase 1', type: 'group', showSummaryBar: false, start: '2026-04-01', end: '2026-04-01' },
  { id: 'a', name: 'Task A', parentId: 'phase', start: '2026-04-02', end: '2026-04-06' },
  { id: 'envelope', name: 'Envelope', type: 'group', start: '2026-04-10', end: '2026-04-10' },
  { id: 'roof', name: 'Roofing', parentId: 'envelope', start: '2026-04-10', end: '2026-04-12' },
];

Milestones ​

tsx
{ id: 'm1', name: 'Go-live', type: 'milestone', start: '2026-06-01', end: '2026-06-01' }

Rendered as a 14px diamond with label to the right. Draggable (move only), no resize handles.

Dependencies ​

Add dependencies on the successor task pointing to predecessor id(s). A predecessor/successor pair is one link; its id is dependencyId(fromId, toId) ("a->b").

typeFrom (predecessor)To (successor)
FS (default)endstart
SSstartstart
FFendend
SFstartend

Links are orthogonal SVG paths with an arrowhead pointing into the successor edge. When the successor's edge is behind the predecessor's, the path doubles back through the row gutter; milestones connect at the diamond's left (start) or right (end) tip. A non-zero lag is drawn as a label on the link (+2d / -1d — override with formatDependencyLag).

tsx
// Simple form (FS, no lag)
{ id: 'b', name: 'Task B', start: '...', end: '...', dependencies: ['task-a'] }

// Object form
{ id: 'b', dependencies: [{ id: 'task-a', type: 'SS', lag: 2, color: '#e11d48', critical: true }] }

color colours the line, arrowhead and label; className is added to the link's <g>; critical adds rg-dependency--critical (heavier, red by default).

Links are drawn but inert by default. Pass any of onDependencyClick, onDependencyHover, onDependencyContextMenu, onDependencyDelete, or a controlled selectedDependencyIds, and each link gets a wide invisible hit stroke (the only part that takes pointer events, and painted under the bars so it never steals a bar drag):

  • Click (or Enter/Space on a focused link) selects it; ctrl/meta-click toggles. Task and link selection are one selection: a plain click on either replaces both. onSelectionChange reports { selectedIds, selectedDependencyIds }.
  • Delete/Backspace while links are selected (and focus is in the chart, outside a text field) fires onDependencyDelete({ dependencies }). The chart does not remove anything — update tasks.
  • Click, context menu and hover also reach onGanttClick / onGanttContextMenu / onGanttHover with a { type: 'dependency', id, from, to, dependency } target.
tsx
const [linkIds, setLinkIds] = useState<string[]>([]);

<GanttChart
  tasks={tasks}
  selectedDependencyIds={linkIds}
  onSelectionChange={(e) => setLinkIds(e.selectedDependencyIds)}
  onDependencyDelete={({ dependencies }) => removeLinks(dependencies.map((d) => d.id))}
/>

Set enableDependencyCreate (or GanttTask.enableDependencyCreate per task, which overrides it) and each bar and milestone gets a connector handle just outside its start and end edge, shown on hover and focus, and on every linkable bar while a link is being drawn. A readOnly task has none.

  • Drag from one handle to another task's handle. A live preview follows the pointer — dashed while it has nowhere to land, solid with a ring once it is over a handle — and the timeline auto-scrolls while the pointer is near the viewport's edges. Dropping on a handle fires onDependencyCreate({ fromId, toId, type, source: 'pointer' }), with the type inferred from the two handles: end→start FS, start→start SS, end→end FF, start→end SF.
  • Escape, a drop on the same task, on a bar body or on empty space cancel with no event.
  • Keyboard: linkable bars are focusable. Press L on a bar, move focus to the target bar (Tab), then Enter for FS or Shift+Enter to choose the type from a small menu (arrow keys, Enter; Escape closes it). Escape, or moving focus out of the chart, cancels. Progress is announced in a polite live region.

The chart adds nothing and checks nothing — not cycles, not duplicates. Validate in the handler, then update tasks.

tsx
<GanttChart
  tasks={tasks}
  enableDependencyCreate
  onDependencyCreate={({ fromId, toId, type }) => {
    if (wouldCycle(fromId, toId)) return;
    setTasks((ts) => ts.map((t) => (t.id === toId
      ? { ...t, dependencies: [...(t.dependencies ?? []), { id: fromId, type }] }
      : t)));
  }}
/>

dependencyTypeForEdges(from, to) is the inverse of DEPENDENCY_EDGES.

Building on links can reuse routeDependency(type, fromX, fromY, toX, toY), buildDependencyPath, DEPENDENCY_EDGES and computeDependencyLinks.

Baseline ​

Show original plan dates as an amber overlay. Enable with showBaseline (default true).

tsx
{
  id: 't1',
  name: 'Foundation',
  start: '2026-04-05',
  end: '2026-04-12',
  baseline: { start: '2026-04-01', end: '2026-04-10', color: '#e6a23c' },
}

See also: Group Summary example · Advanced example